Skip to content

Robotic Refueling Mission

RRM-3 being installed on the JEM airlock slide table in Kibo, 19 February 2019. The payload is shown on the slide table before transfer outside; the NASA record documents the installation, not the internal hardware NASA/David Saint-Jacques. Public domain (NASA / US government work).

The Robotic Refueling Mission was a multi-phase technology development effort by NASA and the Canadian Space Agency to identify and develop the tools, techniques and procedures for refuelling and servicing a satellite not designed to be serviced in orbit [1]. It combined the robotic systems of the International Space Station with the tool design and satellite servicing work of the Exploration and In-space Services projects division at Goddard Space Flight Center. Between 2011 and 2021 two external station payloads housed more than a dozen robotic tools and adapters [1]. NASA describes the Phase 1 configuration as the RRM module, a box covered with activity boards, plus four stowed tools [5].

The tasks demonstrated were cutting lock wires, manipulating fasteners and thermal blanketing, removing caps, connecting to and resealing a fuel port, transferring fluid in zero gravity, and long-term storage of cryogens [1]. Phase 1 added the operation of typical door latches and the mechanical manipulation of valves on a dummy coolant valve panel task board [2]. Phase 1 addressed the steps needed to refuel a legacy spacecraft with storable propellants and the early steps for replenishing cryogens; Phase 2 addressed intermediate steps for cryogen transfer; RRM3 addressed the final steps [1].

Every task was executed by robot operators at NASA JSC and at CSA using the Special Purpose Dexterous Manipulator, which retrieved and operated the tools from the payload [1]. The Phase 1 module reached its work site in three steps: an EVA crew member moved it from the Shuttle payload bay to the SPDM Enhanced ORU Temporary Platform, then the SSRMS used the SPDM to relocate it to ELC4 [2].

ParameterValueSource
Phase 1 module mass250 kg (550 lb)[1]
Phase 1 module envelope838 x 1092 x 1397 mm (33 x 43 x 55 in)[1]
RRM3 Fluid Transfer Module mass318 kg (700 lb)[1]
RRM3 FTM envelope762 x 1143 x 1143 mm (30 x 45 x 45 in)[1]
Tool interfaceSPDM ORU and Tool Changeout Mechanism[1], [2]
Cameras per tool2, orthogonal[1], [2]
Common tool structureTool and Vision Support Structure, providing stowage, electrical and vision interfaces[2]

Ethanol rather than a propellant was flown in Phase 1 to limit risk to the station and its crew [1]. RRM3 by contrast carried roughly 50 liters of liquid methane, a combustible cryogen, which drove both the ground servicing design and the launch site selection [4].

EventDateSource
Phase 1 module launched on STS-135, the final Shuttle flight2011-07
Removed from the Shuttle payload bay by an EVA crew member, the last payload ever removed that way2011-07
Installed on ELC4 by SPDM2011-09
Phase 2 task boards and VIPIR launched on HTV-4 and ATV-52013-08, 2014-07
Phase 2 hardware installed on the RRM module by SPDM2015-04
Phase 1 and 2 hardware removed from the station2017-03
Phase 1 and 2 hardware destroyed on the re-entry of SpaceX CRS-10, except the SCT and Task board 4, returned as pressurized cargo2017
RRM3 Fluid Transfer Module, three tools and a mounting pedestal launched on SpaceX CRS-162018-12-05[1], [4]
SPDM installed the FTM on ELC12018-12
SPDM installed the tool pedestal and tools2019-04
Cryocooler failure; stored liquid methane vented before robotic cryogen testing2019-04
FTM scheduled for de-orbit2022
Phase 1 fluid flown1.7 liters of ethanol[1]
RRM3 cryogen flownapproximately 50 liters of liquid methane[4]

Rows with no marker are from [1].

Two EXPRESS Logistics Carriers hosted the payloads: ELC4 on the starboard-nadir side for Phases 1 and 2, ELC1 on the port-nadir side for RRM3 [1]. RRM3 launched on 5 December 2018 [4].

ItemPhaseFunction
Wire Cutter Tool (WCT)1Cut lock wires between fill and drain valves; a small gripper grasps and manipulates thermal blanketing, and a blade cuts blanket closeout tape
Safety Cap Tool (SCT)1Remove and stow a fill and drain valve safety cap and its seal
EVR Nozzle Tool (ENT)1Open a fuel valve, transfer fluid through it, and close it
Multi-Function Tool (MFT)1Carrier for several small adapters, for tasks such as removing fuel valve caps or a gas plug
Electrical Plug Adapter (EPA)2Capture and remove a connector turnaround plug
Wire Harness Adapter (WHA)2Mate an electrical plug and run a connectivity check
Vent Plug Adapter (VPA)2Insert into a vent line to seal a gaseous line before refuelling
Coolant Line Adapter (CLA)2Mate a coolant fitting to an interface, tethered on a spring reel to simulate hose forces; no coolant transferred
Blind Mate Adapter (BMA)2Connect an array of SMA plugs in a receptacle box
VIPIR2Flexible tube with a camera at an articulatable tip, navigated through conduits of several materials to inspect inside a spacecraft
Cryogen Servicing Tool (CST)3Capture and feed a flexible, non-fixed cryogen hose into a receiver tank
VIPIR23Upgraded cameras; the only RRM tool to transmit video over wifi rather than through the SPDM and SSRMS data lines
MFT23First and only RRM tool with adjustable Camera Positioning Mechanisms, allowing the tool cameras to be extended or pitched per task
Cryogen Coupler Adapter (CCA), Xenon Coupler Adapter (XCA)3Fluid transfer through fixed dedicated supply hoses

Source: [1].

The MFT is the design argument the program makes about mass: exchangeable adapters rather than a separate tool for each task saves mass and volume on a servicing mission [1]. On Phase 1 the MFT carried four adapters, including a tertiary cap adapter for the refuelling task [2]. Exposing a fill and drain valve requires cutting away its closeout multi-layer insulation and removing the tertiary and safety caps with their safety wires cut, which is the sequence the WCT, SCT and MFT were built around.

Task boards carried the work sites [2], [5]. Task board 2 held a tertiary cap and a safety cap with their wires for wire cutting and cap removal, both dummy caps not plumbed into the fluid transfer system, a test port panel for blanket manipulation, and three machine vision tasks: an explosive bolt hole simulation, a Hubble J-hook, and a Hubble door latch [2]. The boards also carried solar cell technology and materials coating demonstrations and machine vision fiducials, including the ARToolKit fiducial and a camera calibration pattern [1].

RRM3 demonstrated zero boil-off storage of liquid methane for nearly six months, of which four months were on orbit [3]. The following were achieved or attempted.

ItemResult
Zero boil-off cryogen storageAchieved, nearly 6 months total, 4 months on orbit
Radio Frequency Mass GaugeMass gauging achieved on the ground and in microgravity
Turbine flowmeterPartially successful on the ground: accurate when it registered flow, but did not always register it; not used on orbit
Liquid and vapor detectors, of the type used on the Superfluid Helium On-Orbit Transfer experimentDistinguished liquid from vapor on the ground and on orbit during storage; ambiguous during ground transfers because of fluid supersaturation
Autogenous pressurization by a wick and heater technique developed at GSFCAchieved on the ground and on orbit
Integrated Multi-Layer InsulationAllowed the receiver dewar cryocooler to reach below 82 K, against a methane triple point of 90.7 K
No-vent transfers with methane5 achieved during ground testing at NASA KSC
Fluid management to orient liquid at the transfer line inlet in microgravityNot tested, no on-orbit transfer occurred
Freezing a cryogen in microgravityNot attempted on orbit; argon and methane were frozen in ground tests

The cryogenic portion of the mission ended early because of electrical problems [3], the proximate cause being a cryocooler failure in April 2019 that forced the stored methane to be vented [1]. Most of the robotic tools were still maneuvered and operated as planned, giving results on the technique for transferring cryogens and manipulating the associated interfaces. Demonstration of the robotic tool interfaces was left to continue as the station schedule allowed, with no cryogen transfer [3].

RRM uses a cold-biased design with a radiator on the back of the enclosure to hold temperature in the hottest environments, and multi-layer insulation plus heaters to hold component temperatures in the worst cold cases [2]. Heater power comes from three independent sources at three voltages, reflecting the three phases of the payload’s life.

SourceAllocationNotes
Shuttle, 28 V230 W at maximum voltage, about 216 W at nominal4 circuits on the fluid transfer system plate; each circuit controlled by two Elmwood mechanical thermostats in series, cycling between +25 and +30 degrees C
ISS, 120 V290 W at maximum voltage, about 245 W at nominalTwo feeds, on the fluid transfer system plate, the fluid flex line, and the enclosure next to the plumbed fill and drain valves
OTCM, 15 V5 W per camera, two per tool, and 10 W per tool electronics boxCamera thermostats set at -25 to -16 degrees C, tool electronics box at -32 to -26 degrees C

Values from [2]. Tool heaters are powered only through the OTCM, so no tool heater power is available while a tool is stowed on the tool stowage bench inside the RRM enclosure. The thermal cases are defined with the tools stowed and unheated for the non-operating cases, and with the MFT and ENT deployed and operating and the WCT and SCT stowed for the operating cases.

Ground operations and procedure development

Section titled “Ground operations and procedure development”

Preparation for each phase ran for years before launch: goals were converted to preliminary hardware designs, prototypes of some tools and adapters were tested on industrial robots at Goddard to refine the design, and once high-fidelity CAD or hardware was available Goddard robot operators wrote draft procedures giving explicit detail on how to maneuver and operate the tools [1]. For RRM3 the ground campaign extended to building a methane servicing capability that did not previously exist [4].

Hardware testing was done in Goddard’s Servicing Technology Center, using a six degree-of-freedom industrial arm as a stand-in for one SPDM arm together with an OTCM Simulator supplied by MDA, the builder of the SPDM end effector [1]. That combination let prototype, engineering design unit, flight spare and flight tools be operated as they would be in space, and supported both nominal and contingency procedure development. The tool thermal design assumes this same deployed-and-operating versus stowed distinction in its hot and cold cases [2].

Every RRM tool presents the same OTCM interface and the same Tool and Vision Support Structure, which is what makes one procedure format work across the set [2]. Goddard robot operators designed the robotic maneuvers and determined the OTCM commands, operators at JSC and CSA translated them for SSRMS and SPDM, and to make that translation straightforward every maneuver was expressed relative to the previous location rather than as Cartesian positions or joint angles [1], [5].

At least one campaign on MDA’s Ground Trainer was run for each phase, on robotic hardware and software representative of the station systems, against the same SPDM interfaces the tool thermal design assumes for power and stowage [2]; MDA engineers converted the Goddard procedures for the Ground Trainer robot first, and in some cases the torques, forces or step order in the Goddard procedures were not achievable with SPDM [1].

The Goddard robot control software includes a visualization of robot, tool drive, tools and payloads. For RRM3 it was extended to display and control simulated cameras, including the tool cameras, and to set the position and orientation of the tool tip and any attached adapter [1]. That allowed procedure development to start before hardware existed, and let tasks be evaluated with fewer people and less risk once it did; the simulation does not verify contact forces, OTCM turns and torques, or the motion of flexible hoses. Flexible hose handling is exactly what the Cryogen Servicing Tool was built to exercise, capturing a flexible, non-fixed cryogen hose and feeding it into a receiver tank.

NASA KSC loaded approximately 50 liters of liquid methane into the RRM3 payload’s source dewar before launch [4]. KSC had fueled rockets and payloads before but had never done so with liquid methane, so the ground support equipment and the processes were developed from nothing. All ground operations were controlled locally by operators, with no automation and no software control of the ground support equipment. Pre-flight ground testing with liquid methane was performed both on an engineering demonstration unit and on the flight payload, also at KSC. Autogenous pressurization was demonstrated both on the ground and on orbit [3].

The program’s transferable outputs are the tool set and the operations method rather than a vehicle. Named results are the exchangeable-adapter architecture that replaces one tool per task [1], [2]; robotic cutting of lock wire and closeout blanket to expose a fill and drain valve that was never designed for servicing; a poseable borescope for interior inspection through spacecraft conduits [1]; wifi video off a robotic tool, avoiding the manipulator data path; adjustable camera positioning on a tool; and, on the fluid side, zero boil-off cryogen storage, radio frequency mass gauging in microgravity, autogenous pressurization by wick and heater, and integrated multi-layer insulation [3].

NASA states the objective as giving satellite owners the means to diagnose problems on orbit, fix anomalies and keep instruments working longer, and as seeding a commercial servicing industry [5]. RRM also established the station as a route to raise technology readiness for servicing hardware, and led to further technology partnerships between the Goddard servicing division and the ISS program [1]. The lessons are recorded as being applied to the designs, operations concepts and ground test methodology of On-orbit Servicing, Assembly and Manufacturing 1 and of Mars Sample Return. On the cryogenic side the demonstrated items were autogenous pressurization, radio frequency mass gauging and integrated multi-layer insulation [3].

The published lessons are specific. Designing robotic tools for the space environment requires attention to materials, indicators, and the differences between ground and flight use cases and environments [1]; the thermal case is one instance, where a tool loses all heater power the moment it is stowed [2]. Where the on-orbit operations window is limited, spending time and high-fidelity hardware on ground testing is what buys it back [1]; the RRM3 fluid campaign spent five ground no-vent transfers to that end [3]. Camera view quality, frame rate and position requirements are driven by the needs of troubleshooting rather than by nominal operations [1], which is the reasoning behind the adjustable camera positioning on MFT2 and the wifi video path on VIPIR2. Detailed hardware manuals, nominal and contingency procedures, and clearly defined operations team roles and protocols determine efficiency. The RRM3 ground servicing campaign reached the same conclusion from the fluid side, where every operation was run manually by operators with no software control [4].

References

  1. Tomlinson, Z., Gallagher, W., Cassidy, J., Roberts, B., Facciol, K. and Easley, J. (2021). Lessons for Future In-Space Telerobotic Servicing from Robotic Refueling Mission. NASA, 20210022255. Source
    BibTeX
    @inproceedings{tomlinson2021lessons,
      title = {Lessons for Future In-Space Telerobotic Servicing from Robotic Refueling Mission},
      author = {Tomlinson, Zakiya and Gallagher, William and Cassidy, Justin and Roberts, Brian and Facciol, Kristen and Easley, Joseph},
      year = {2021},
      institution = {NASA},
      number = {20210022255},
      url = {https://ntrs.nasa.gov/citations/20210022255},
      booktitle = {2022 IEEE Aerospace Conference (AERO)},
      doi = {10.1109/aero53065.2022.9843499},
      pages = {1-17}
    }
  2. Gregory, T. H. and Newman, M. (2011). Thermal Design Considerations of the Robotic Refueling Mission (RRM). NASA, 20110013452. Source
    BibTeX
    @inproceedings{gregory2011thermal,
      title = {Thermal Design Considerations of the Robotic Refueling Mission (RRM)},
      author = {Gregory, Teri H. and Newman, Miles},
      year = {2011},
      institution = {NASA},
      number = {20110013452},
      url = {https://ntrs.nasa.gov/citations/20110013452},
      booktitle = {41st International Conference on Environmental Systems},
      doi = {10.2514/6.2011-5072}
    }
  3. Breon, S. R., Boyle, R. F., Francom, M. B., DeLee, C. H., Francis, J. J., Mustafi, S., Barfknecht, P. W., McGuire, J. M., Krenn, A. G., Zimmerli, G. A. and Hauser, D. M. (2020). Robotic Refueling Mission-3---an overview. IOP Conference Series: Materials Science and Engineering. Source
    BibTeX
    @article{breon2019robotic,
      title = {Robotic Refueling Mission-3---an overview},
      author = {Breon, S. R. and Boyle, R. F. and Francom, M. B. and DeLee, C. H. and Francis, J. J. and Mustafi, S. and Barfknecht, P. W. and McGuire, J. M. and Krenn, A. G. and Zimmerli, G. A. and Hauser, D. M.},
      year = {2020},
      journal = {IOP Conference Series: Materials Science and Engineering},
      volume = {755},
      pages = {012002},
      doi = {10.1088/1757-899X/755/1/012002},
      url = {https://doi.org/10.1088/1757-899X/755/1/012002}
    }
  4. Krenn, A., Stewart, M., Mitchell, D., Dixon, K., Mierzwa, M. and Breon, S. (2019). Flight Servicing of Robotic Refueling Mission 3. IOP Conference Series: Materials Science and Engineering. Source
    BibTeX
    @article{krenn2019flight,
      title = {Flight Servicing of Robotic Refueling Mission 3},
      author = {Krenn, A. and Stewart, M. and Mitchell, D. and Dixon, K. and Mierzwa, M. and Breon, S.},
      year = {2019},
      journal = {IOP Conference Series: Materials Science and Engineering},
      url = {https://ntrs.nasa.gov/citations/20190027566}
    }
  5. Boyle, R., DiPirro, M., Tuttle, J., Francis, J., Mustafi, S., Li, X., Barfknecht, P., DeLee, C. H. and McGuire, J. (2015). Cryogenic Autogenous Pressurization Testing for Robotic Refueling Mission 3. NASA Goddard Space Flight Center, 20150016072. Source
    BibTeX
    @techreport{boyle2015cryogenic,
      author = {Boyle, R. and DiPirro, M. and Tuttle, J. and Francis, J. and Mustafi, S. and Li, X. and Barfknecht, P. and DeLee, C. H. and McGuire, J.},
      title = {Cryogenic Autogenous Pressurization Testing for {Robotic Refueling Mission 3}},
      institution = {NASA Goddard Space Flight Center},
      number = {20150016072},
      year = {2015},
      url = {https://ntrs.nasa.gov/citations/20150016072}
    }

Further reading

  • Boyle, R., Breon, S., Francom, M., DeLee, H., Francis, J., Mustafi, S., Barfknecht, P., McGuire, J., Krenn, A. and Zimmerli, G. (2019). Robotic Refueling Mission 3: Cryogenic Demonstration Subsystem Operations. NASA Goddard Space Flight Center. Source
  • (2026). NASA ISAM: RRM 1 and 2. nasa.gov/isam/rrm-1-2
  • NASA. (2020). Cross-Program Design Specification for Natural Environments (DSNE), Revision G. NASA Marshall Space Flight Center. Source
  • Lear, D. M., Hoffman, K. D., Hyde, J. L. and Collins, C. M. (2019). Bumper: A Tool for Analyzing Spacecraft Micrometeoroid and Orbital Debris Risk. NASA. Source
  • O'Neill, P. M., Golge, S. and Slaba, T. C. (2014). Implementing the Badhwar-O'Neill Galactic Cosmic Ray Model for Spacecraft Analysis. NASA. Source